Peru sustainability project

What are we trying to do?

The aim is to make the Diocese of Peru less dependent on outside aid in the long term.

In the Peruvian capital, Lima, the church of Jesus the Saviour is a three storey building with a worship space and a meeting hall downstairs. The two floors above the meetng hall were unfinished, without plumbing or electrical fittings, used only for storage.

The plan was to create some small apartments on the upper floor, replacing the corrugated plastic roof with reinforced concrete, making a rooftop area for washing and drying laundry.

One ground floor entrance to the building would be remodelled, such that tenants can access their bedsits without disturbing church activities.

This project would provide accommodation for students or young employees, much-needed in the area, and significant rental income to help pay some of the priests in the diocese. In the long term the diocese is working towards self-sustainability by means of projects like these.

The total budget is £32,000. The major part of this is coming from the Cathedral of the Holy Trinity in Gibraltar, but contributions are needed from the other churches of the Archdeaconry.

Bishop Jorge and Bishop Victor are supervising the project.

Before work began...

external view of the building

Outside: the worship area is on the right, the meeting hall on the left

storage area above the meeting hall

Part of the storage area above the meeting hall

October 2025

framework for new storey

Framework for the first new ceiling/floor

adding new storey

Getting ready to pour cement

pouring cement

Adding cement to the first new ceiling/floor

new stairs

New stairs to get to the new level

December 2025

dividing the space

Starting to create the bedsits

Bishops and builder

Bishops and builder

June 2026

another level

Taking it to another level

outside view

The view from outside - compare with the first picture above

July 2026 A

another level

This area has now been plastered.

outside view

The view from outside - compare with previous

July 2026 B

another level

The flat roof will be used for laundry.

outside view

Plastering progresses inside

To be continued...

The work is progressing well.

Funds sent so far are as follows:
2024 - Tenerife North £2400
September 2025 - Holy Trinity Cathedral - £6,400
November 2025 - other chaplaincies - £2,961
January 2026 - Holy Trinity Cathedral - £7,000
April 2026 - other chaplaincies - £4026
April 2026 - Holy Trinity Cathedral £7,000
June 2026 - Barcelona £2,750

The heavy work of making the two new levels has been done, but there is still plastering, plumbing and electricity to sort out.

Bishop Victor spoke at the Archdeaconry Synod in January 2026 and answered questions about the project.

Chaplaincies and individuals are invited to make further donations via the diocesan office in London, clearly tagged 'Peru project'.

Individuals may donate via the Cathedral using this QR code: